By Umer Bhatti |

The News has learnt Pepco is paying the highest price of Rs38 (Energy Purchase Price (EPP), fuel plus variable operation and maintenance cost) to the Kotri Power Plant for generation from its unit 1-2, which is being run by the company on much expensive High Speed Diesel (HSD). On the other hand, the company is paying a minimum of Rs0.5 to UCH power plant, a gas-run IPP, for the purchase of energy up to first 153MW of power generated. The rate of electricity keeps on increasing as the power plant produces more electricity than the above mentioned capacity because the slab of the power purchase increases in the same way as the consumer slabs to pay the electricity bill increases.
Read More!